Storm Drainage Flow and Inlet Capacity

Read a drainage worksheet and check the flow balance through a simple inlet network.

Inputs and Prerequisites

Catchment boundaries, design storm basis, grading, flow paths and inlet or pipe information.

Work Steps

  1. Inputs
  2. Model or detail
  3. Independent check
  4. Review record
  1. Identify each source area and route runoff using the site grading.
  2. Document the flow estimate and compare it with inlet capture or conveyance assumptions.
  3. Track bypass flow to the downstream route and identify overflow conditions.

Worked Example or Review Exercise

A hypothetical inlet receives 18 L/s and captures 12 L/s in a specified scenario. Carry the 6 L/s bypass downstream and verify that the worksheet preserves the balance.

Output Checks and Common Errors

Check units and confirm whether the model accounts for bypass. Review current local design rainfall and acceptance criteria.