Intermediate

Screening New Penetrations Against Structural Drawings

Locate the opening using project grids and elevations. Use the example below to practice the review and record an output that another reviewer can reproduce.

Inputs and Prerequisites

Latest structural drawings, opening request, sleeve dimensions and services layout.

Review Workflow

  1. Grid location
  2. Plan projection
  3. Section check
  4. Disposition
  1. Locate the opening using project grids and elevations.
  2. Check nearby reinforcement, tendons and structural details.
  3. Log structural disposition and firestop review as separate actions.

Worked Example

A 120 mm sleeve center is 180 mm from the face of a beam shown on plan. The near sleeve edge is 120 mm from that face in projection. Mark the opening in a section too, since the plan tells nothing about elevation or hidden reinforcement.

Output Checks and Common Errors

Use verified as-built information before construction. Treat plan clearance as a coordination measurement.