Coordinating Buried Utilities at Crossings
Convert invert levels to outer pipe envelopes using verified wall and diameter data. Use the example below to practice the review and record an output that another reviewer can reproduce.
Inputs and Prerequisites
Survey datum, pipe outside diameters, two invert elevations and location confidence.
Review Workflow
- Datum
- Two envelopes
- Clear gap
- Verify crossing
- Convert invert levels to outer pipe envelopes using verified wall and diameter data.
- Compute the clear gap at the actual crossing.
- Record survey uncertainty and assign verification responsibility.
Worked Example
The surveyed outside top of the lower line is 102.14 m. The proposed outside bottom of the upper line is 102.42 m, giving 280 mm of vertical clearance. If the lower survey elevation can be 60 mm higher, 220 mm remains under that assumption.
Output Checks and Common Errors
Compare elevations in one datum. Record required clearance and field verification as separate items.